Experienced facilitators understand both the challenge and value of getting a group to focus on the same thing at the same time. For most project-related meetings, Work Breakdown Structure (WBS) provides a simple method to increase focus. According to Goldblatt’s Triple Constraint Theory, mitigate risk through focused discussion on the cost, schedule, and scope of discrete portions of the project rather than the entire project at once.

Work Breakdown Structure represents a method that groups the project’s distinct work elements to help organize and define the total work scope of the project. While many experts suggest that a WBS element may be a product, data, a service, or any combination; at a detailed level strive to use verbs, and terms that represent the work and activity that needs to be completed. Work Breakdown Structure also provides framework for detailed cost estimating and control along with providing guidance for schedule development and control. Additionally WBS enables the project manager or product owner to dynamically revise and update as needed.

Each descending level of the Work Breakdown Structure represents an increasingly detailed definition of the project work. Note this illustrative WBS for building a house. Break work down into separate elements, the total sum of which represents all the work necessary to build the house.

Work Breakdown Structure Increases Focus and Reduces Scope Creep

Work Breakdown Structure – House Construction

In summary, the Work Breakdown Structure:

  • Ensures you have defined the significant aspects that make up the project
  • Provides a framework for organizing and managing project scope
  • Provides feedback for planning and controlling costs and scheduling

Benefits for Portfolio or Program Management

When you have numerous projects being performed simultaneously, each project competes for the limited resources available. WBS enables you to review project details and distinguish one project’s needs from others within your organization. Therefore, you are better enabled to identify resource requirements and allocate resources more effectively.

Preparing a Work Breakdown Structure

Here are some suggested steps for preparing a Work Breakdown Structure:

  1. Always start with the end in mind, the project deliverable. Identify final project products necessary for achieving project success.
  2. Identify the major aspects necessary for project completion and success.
    • These are items that by themselves do not complete the project need but, when combined, make up a successful project
    • Examples shown previously include structural, electrical, and plumbing
  3. Build out additional levels of detail for managing and controlling the project requirements.
    • Remember that each project is different, thus each WBS will be different
    • WBSs from previous projects can be used as templates, but remember that the management philosophy and the level of detail may be different from project to project
    • Understand your controlling and reporting requirements
  4. Review and refine the Work Breakdown Structure until the stakeholders agree with the level of project planning and reporting.
    • Remember that no matter how detailed your WBS is, there are planning and reporting restrictions created by a WBS.
    • See below for an example of the detail you need contrasted with what management may need for reviews.

      Work Breakdown Structure Increases Focus and Reduces Scope Creep

      Work Breakdown Structure – Management Needs

In developing a Work Breakdown Structure, realize that there are multiple ways to develop a WBS for any given project. Some ways might be better than others, but the two most important items apply to both:

  1. The Work Breakdown Structure must contain all approved scope and
  2. The Project Manager must develop the Work Breakdown Structure to reflect the way you intend to manage the project.

Helpful WBS templates HERE:

Chief Collaboration Officers

Granted, much of the suggested material above is the responsibility of the session leader. But if they won’t do it, you better. Remember, it’s worth thousands and thousands of dollars to promote more collaborative work. Harvard Business Review states further that collaboration may answer many of your biggest business challenges. They encourage leaders to promote collaborative work and teamwork, and suggest . . .

“. . . we believe that the time may have come for organizations to hire chief collaboration officers.”

______

Don’t ruin your career by hosting bad meetings. Sign up for a workshop or send this to someone who should. MGRUSH workshops focus on meeting design and practice. Each person practices tools, methods, and activities daily during the week. Therefore, while some call this immersion, we call it the road to building high-value facilitation skills.

Our workshops also provide a superb way to earn up to 40 SEUs from the Scrum Alliance, 40 CDUs from IIBA, 40 Continuous Learning Points (CLPs) based on Federal Acquisition Certification Continuous Professional Learning Requirements using Training and Education activities, 40 Professional Development Units (PDUs) from SAVE International, as well as 4.0 CEUs for other professions. (See workshop and Reference Manual descriptions for details.)

Want a free 10-minute break timer? Sign up for our once-monthly newsletter HERE and receive a free timer along with four other of our favorite facilitation tools.

______

With Bookmarks no longer a feature in WordPress, we need to append the following for your benefit and reference